Compute The Capacity Jobs Per Day For The Following Situation A Workstation With

Compute the capacity (jobs per day) for the following situation: A workstation with 8 machines in parallel, each having a mean process time of two hours. There are two seven-hour shifts. Lunch and breaks take one hour per shift. The machines have a mean time to failure of 100 hours with a mean time to repair of four hours.   

Posted in Uncategorized