Compute, the ES, LS, EF, LF, slack and draw the network diagram. In addition, identify the critical path.

ActivityActivity DescriptionDuration (Days)Preceding Activities

ADetermine User Needs2-

B

Review Software and languages

2-

CPurchase Software1B

DDesign format and style3A,C

EWrite programs5D

FReview Outcome product with user1E

GMake revisions2F

HSelect server site1-

IInstall on server and test2G