Solve each of the following variation problems by setting up a formula to express the relationship, finding the constant, and then answering the question. 

The time required to do a job varies inversely as the number of people working. It takes 5hr for 7 bricklayers to build a park well. How long will it take 10 bricklayers to complete the job? 